Today---Receive from Fastenal via UPS the hardware needed to finish unistrut on stalls. Cut all steel for trap. Installed conduit for DCU/Cycler in 2 ranges and boxes mounted on top of DCU. Drilled holes in plywood fascia for Ret. Motor power cords.
Sharp Shooters of Roswell - Range Installation
Friday, October 29, 2010
Thursday, October 28, 2010
Thursday, October 21, 2010
Wednesday, September 22, 2010
Wednesday, September 22
Second crew arrived from Action Target to assist with installation since Action didn't get all the parts here last Monday. Currently we have baffles being installed in the tactical range and trap is getting started in the same range.
Over 200+ baffle plat was brought into the range yesterday, along with other parts and pieces of the parts. All parts have to be hand carried into the range, nothing can be pushed through the 47" opening that was left for us to bring in parts.
Over 200+ baffle plat was brought into the range yesterday, along with other parts and pieces of the parts. All parts have to be hand carried into the range, nothing can be pushed through the 47" opening that was left for us to bring in parts.
Thursday, September 16, 2010
Tuesday, September 14, 2010 - Offload, Inventory, Layout
Today we off loaded the 4th truck, which we are still missing some very important parts. Chambers have not arrived, which we had planned on starting traps and baffles.
Inventory is being worked on as well as moving materials into building through 47" opening. We will have to move everything into the building by hand.
Inventory is being worked on as well as moving materials into building through 47" opening. We will have to move everything into the building by hand.